Method of Statement

Bitumen Primer, SBS Membrane & Protection Layer

Over levelled and cured PCC, we apply one coat of bitumen primer all along the surface and let it dry for 2-3 hours until it becomes tack free. Once the primer dries, we apply 4mm SBS membrane along horizontal and vertical surfaces, keeping a constant 100mm overlap throughout the area, followed by a second membrane layer applied the same way.

  • Horizontal surfaces covered with a protection screed all along the surface
  • Vertical surfaces protected with 3mm protection board, 100mm overlap
  • Sub-structure waterproofing with torch-applied membrane & protection board
  • Pile cap waterproofing treatment to prevent water ingress
Bitumen primer and SBS membrane application on a roof
Step Wise Process

Waterproofing Application — Step by Step

01

Bitumen Primer

Applied on the clean surface and allowed to dry completely.

02

SBS Membrane

Surface heated and membrane unrolled using torch for proper adhesion.

03

Damp Proofing

Coating applied on the external surface to protect against moisture & seepage.

04

Protection & Warranty

Screed or protection board applied, followed by final inspection.

Roof combo waterproofing layer diagram — waterproofing membrane, insulation board, primer and concrete slab
Related Services

Explore More of What We Do

Ready to get a quote for roof combo waterproofing?

Send us your project details and our engineering team will respond with a free site inspection and written scope of work.

Request a Free Quote